Current Status: work continues on the preliminary punch list and finish work. Coordination of the Police department move is ongoing. Are we on time: No. The contractor is behind in wrapping up the building. The Police Department is scheduled to
Read MorePolice Station Project Updates
May 2019
Current Status: A preliminary punch list was generated. Finish work and landscaping is still ongoing. Coordination of E911 and moving the Police Department into the building has begun. Are we on time: No, contractor appears to be about 30 days
Read MoreApril 2019
Current Status: The work is wrapping up! The finish work inside the building including flooring, painting, hardware installation, delivery and installation of the Dispatch consoles continues. Electrical, HVAC and plumbing work inside the building is ongoing. Procurement of furniture has
Read MoreMarch 2019
The Carport concrete was poured, as well as the concrete for the jail cell beds and booking room benches. The wall protection, metal stud jail ceilings, gypsum board in the sally port, the overhead doors, the armory bullet proof door,
Read MoreFebruary 2019
Installation of the gypsum board walls, bullet resistant panels, security mesh at ceilings and walls, the acoustical ceiling grid, attic stairs, window trim and casework were complete as well as sally port gypsum walls and ceiling. The pitch pockets and
Read MoreJanuary 2019
The leaching Field was constructed and connected via the Forced Main to the Pump Chamber and Leach Field. Septic and Pump Tanks were back filled and tested for compaction. Bollards were installed at the electrical service transformer. The car port
Read MoreDecember 2018
December saw 4 days of weather impact and with the average temperature being 35 degrees, Page Construction began providing temporary heat on December 17. Excavation and installation of the septic tank and pump chamber is in progress. Excavation and back
Read MoreNovember 2018
Above average precipitation did have a slight impact on the schedule, rain occurred on ten working days of the project. East and West parking areas were excavated and backfilled. Columbia Gas, thanks to the help of Senator Timilty and Representative
Read MoreSeptember 2018
In September we saw a lot of progress on the project. The slab was poured and a few walls went up. Final decisions on materials were made including siding, paint, lockers, and flooring. These items are being ordered, with special
Read More