The Carport concrete was poured, as well as the concrete for the jail cell beds and booking room benches. The wall protection, metal stud jail ceilings, gypsum board in the sally port, the overhead doors, the armory bullet proof door, casework and exterior ventilation louvers were all installed. The sally port and garage interior north wall were insulated. The store front system at the front vestibule was installed. The epoxy floors were completed, and the floors are being prepped for the VCT flooring and the carpet was delivered. Most walls have at least one coat of paint. Sinks were installed. The Building Management System controls to the roof top units were connected. Grills, diffusers and louvers in ceilings were installed. The exit signs, fire alarms, occupancy sensors, lighting, camera conduit in jail cells and booking were completed as well as underground conduit and tagged wall plates. The Generator was started, tested by manufacturer representative and observed by the commissioning agent. Excavation and grading began at parking lot.
Are we on time? Yes
Are we on budget? Yes
Next Steps: Work continues on the interior and exterior of the building. The committee is working with ACG and Chief Bukunt on FF&E procurement items.