September 2018

In September we saw a lot of progress on the project. The slab was poured and a few walls went up. Final decisions on materials were made including siding, paint, lockers, and flooring. These items are being ordered, with special attention to items with a long lead time. Weekly project meetings are held with the Project Management Team, Design Team and the General Contractor.

Are we on time? Yes

Are we on budget? Yes

Next Steps: Coordination with National Grid and Columbia Gas continues to be a priority. Working to make the building weather tight before winter is ongoing.