May 2019

Current Status: A preliminary punch list was generated. Finish work and landscaping is still ongoing. Coordination of E911 and moving the Police Department into the building has begun.

Are we on time: No, contractor appears to be about 30 days behind schedule.

Are we on budget: Yes

Next steps: Coordination of E911 and moving dispatch from the current building to this one are being coordinated with all parties. Finish work (hardware installation etc) is ongoing and work has begun on a preliminary punch list.