We are proud to announce the launch of our NEW Autism Awareness Program. This Autism Awareness Program is an initiative of the Avon Police Department to allow members of our community to voluntarily identify those with Autism Spectrum Disorder (ASD)
Read MoreAuthor: Kayla Rochon
2020 Avon Police Quality of Service Survey Results
Message from Chief Jeff Bukunt I am pleased to share the results of the 2020 Avon Police Quality of Service Survey. The survey was created based upon our strong belief that it is important for our department to gauge public
Read MoreSingle Motor Vehicle Crash
On 03 February 2020, at approximately 12:00 noon, members of the Avon Police Department and Fire Department responded to the area of North Main, Route 28, near the Randolph town line for the report of a single motor vehicle crash.
Read MoreJune 2019
Current Status: work continues on the preliminary punch list and finish work. Coordination of the Police department move is ongoing. Are we on time: No. The contractor is behind in wrapping up the building. The Police Department is scheduled to
Read MoreMay 2019
Current Status: A preliminary punch list was generated. Finish work and landscaping is still ongoing. Coordination of E911 and moving the Police Department into the building has begun. Are we on time: No, contractor appears to be about 30 days
Read MoreApril 2019
Current Status: The work is wrapping up! The finish work inside the building including flooring, painting, hardware installation, delivery and installation of the Dispatch consoles continues. Electrical, HVAC and plumbing work inside the building is ongoing. Procurement of furniture has
Read MoreMarch 2019
The Carport concrete was poured, as well as the concrete for the jail cell beds and booking room benches. The wall protection, metal stud jail ceilings, gypsum board in the sally port, the overhead doors, the armory bullet proof door,
Read MoreFebruary 2019
Installation of the gypsum board walls, bullet resistant panels, security mesh at ceilings and walls, the acoustical ceiling grid, attic stairs, window trim and casework were complete as well as sally port gypsum walls and ceiling. The pitch pockets and
Read MoreJanuary 2019
The leaching Field was constructed and connected via the Forced Main to the Pump Chamber and Leach Field. Septic and Pump Tanks were back filled and tested for compaction. Bollards were installed at the electrical service transformer. The car port
Read MoreDecember 2018
December saw 4 days of weather impact and with the average temperature being 35 degrees, Page Construction began providing temporary heat on December 17. Excavation and installation of the septic tank and pump chamber is in progress. Excavation and back